Sri Marg work not yet complete as Srimandir Heritage Corridor inauguration nears!

Local residents have expressed dissatisfaction over the alleged shoddy work done in haste ahead of the mega opening of the project on January 17, 2024.

Sri Marg work under progress in Puri

Though only four days have been left for the opening of the Srimandir Parikrama Project (Srimandir Heritage Corridor project) in Puri, construction of ‘Sri Marg’ is yet to be completed. Meanwhile, local residents have expressed dissatisfaction over the alleged shoddy work done in haste ahead of the mega opening of the project on January 17, 2024.

The district administration had earlier assured that all the works of the Srimandir Parikrama Project would be completed by January 12. However, many works are yet to be completed. As per reports, paver blocks are still being installed on 800 metres of Sri Marg. Moreover, a huge amount of sand is still piled on the spot.