Co contracted for Trisulia bridge work asks for extra Rs 19 cr

Bhubaneswar: HES Infrastructure Private Limited, which was awarded the construction work of a three-lane bridge over Kathajodi river, has submitted a bill of Rs 10 crore on account of estimation cost for change in design to the State government. Though the Hyderabad-based company in its agreement with the Odisha government stated that it would not […]

126748

Bhubaneswar: HES Infrastructure Private Limited, which was awarded the construction work of a three-lane bridge over Kathajodi river, has submitted a bill of Rs 10 crore on account of estimation cost for change in design to the State government.

Though the Hyderabad-based company in its agreement with the Odisha government stated that it would not charge anything for a change in design of the bridge, the Rs 10 crore bill has raised eyebrows among many.