Haridaspur-Paradip rail project: Luna bridge work to be over by Oct-end

Bhubaneswar: The under construction bridge over Luna river, a part of the 82-km Haridaspur-Paradip rail project, will be completed by October-end. This was informed by the executive director of the rail project during a review meeting here chaired by senior BJD leader and Kendrapara MP Baijayant Panda. Out of Rs 1559 allocation towards the rail […]

rail line

Bhubaneswar: The under construction bridge over Luna river, a part of the 82-km Haridaspur-Paradip rail project, will be completed by October-end. This was informed by the executive director of the rail project during a review meeting here chaired by senior BJD leader and Kendrapara MP Baijayant Panda.

Out of Rs 1559 allocation towards the rail project, Rs 787.15 crore has been spent by August 2016, the meeting was informed.