Delay in Odisha govt approvals led to tardy progress of 2nd Brahmani bridge: Gadkari

New Delhi/Bhubaneswar: Replying to Chief Minister Naveen Patnaik on construction of second bridge over river Brahmani in Rourkela, Union Road Transport Minister Nitin Gadkari today said delay in granting statutory approval from Odisha Government including forest clearance and land acquisition has led to non- commencement of project on Birmitrapur-Barkote section of NH-143. In a letter […]

Nitin Gadkari

New Delhi/Bhubaneswar: Replying to Chief Minister Naveen Patnaik on construction of second bridge over river Brahmani in Rourkela, Union Road Transport Minister Nitin Gadkari today said delay in granting statutory approval from Odisha Government including forest clearance and land acquisition has led to non- commencement of project on Birmitrapur-Barkote section of NH-143.

In a letter to Patnaik, Gadkari said "I was surprised and pained to receive your letter and media reports suggesting the delay on part of NHAI. I may like to clarify that all these projects are delayed for want of forest clearance and land issues.”