Delay in construction of Gurupriya Bridge raise speculations

Malkangiri: While the Works Department has assured that the Gurupriya bridge construction in Chitrakonda of Malkangiri will end by April end, it has been alleged that the construction company engaged for the purpose has not deployed adequate resources necessary for targeted completion of the project. Earlier on March 29, the Malkangiri Collector, in a letter […]

Gurupriya-bridge

Malkangiri: While the Works Department has assured that the Gurupriya bridge construction in Chitrakonda of Malkangiri will end by April end, it has been alleged that the construction company engaged for the purpose has not deployed adequate resources necessary for targeted completion of the project.

Earlier on March 29, the Malkangiri Collector, in a letter to the Engineer-in-Chief-cum-Secretary to Government, Works Department had alleged that after a fall in the water level at Balimela Reservoir, the company - Royal Infraconstruction Limited, Kolkata, failed to mobilise cranes for nearly 15 days.