Second n-plant at Kudankulam to restart by March-end

Chennai: India’s atomic power plant operator will restart its second 1,000 MW unit at Kudankulam in Tamil Nadu in two weeks’ time while the first unit of similar capacity will be stopped for refuelling in mid-April, a senior official said on Monday. He also said that the first pouring of concrete for construction of the third […]

kundankulam

Chennai: India's atomic power plant operator will restart its second 1,000 MW unit at Kudankulam in Tamil Nadu in two weeks' time while the first unit of similar capacity will be stopped for refuelling in mid-April, a senior official said on Monday.

He also said that the first pouring of concrete for construction of the third reactor facility will be in May-end.